Location Highlights

STRUCTURE NO. 146.1: GSP OVER SOUTH ORANGE AVENUE

IMPROVEMENTS:

  • Reconstruction of median outside barrier
  • Milling and resurfacing of bridge and approaches

CONSTRUCTION:

  • Construction work to be performed in six (6) stages
  • Temporary traffic shifts will be utilized to facilitate the work
  • Work to begin on or about Fall 2018

Location Updates

February 7, 2020

  • During the week of 02/10/20 through 02/17/20, bridge work will continue on northbound and southbound Garden State Parkway at South Orange Avenue in dedicated right shoulder work zones.

January 31, 2020

  • During the week of 02/03/20 through 02/17/20, bridge work will continue on northbound and southbound Garden State Parkway at South Orange Avenue in dedicated right shoulder work zones.