Location Highlights

STRUCTURE NO. 146.0: GSP OVER 14TH AVENUE

IMPROVEMENTS:

  • Reconstruction of median barrier
  • Milling and resurfacing of left shoulders and lanes on bridge and approaches

CONSTRUCTION:

  • Construction work to be performed in six (6) stages
  • Temporary traffic shifts will be utilized to facilitate the work
  • Work to begin on or about Fall 2018

Location Updates

July 1, 2022

  • All work has been completed.
1
2
3

92
Translate »