Location Highlights

STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)

IMPROVEMENTS:

  • Reconstruction of deck, sidewalks, railings/parapets and lighting
  • Roadway milling and resurfacing of East Passaic Avenue at both approaches
  • Guide rail, curb, sidewalk, fencing and traffic striping on East Passaic Avenue

CONSTRUCTION:

  • Construction work to be performed in four (4) stages
  • Temporary traffic shifts will be utilized to facilitate the work
  • Work to begin on or about Summer 2019

Location Updates

October 2, 2020

  • During the weeks of 10/05/20 through 10/12/20, bridge deck reconstruction work will continue as well as curb, sidewalk and guide rail construction on the bridge over the Garden State Parkway. Work will be supported by Nutley Police as necessary.

September 25, 2020

  • During the weeks of 09/28/20 through 10/05/20, bridge deck reconstruction work will continue as well as curb, sidewalk and guide rail construction on the bridge over the Garden State Parkway. Work will be supported by Nutley Police as necessary.

1

23
24
25
26
27

92
Translate »