Location Highlights

STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET

IMPROVEMENTS:

  • Reconstruction of deck, sidewalks, parapets and lighting
  • Roadway milling and resurfacing of Montgomery Street at both bridge approaches
  • Sidewalk, curb, handicap ramp and traffic striping of Montgomery Street

CONSTRUCTION:

  • Construction work to be performed in three (3) stages
  • Temporary traffic shifts will be utilized to facilitate the work
  • Work to begin on or about January 2019

Location Updates

January 24, 2020

  • During the week of 02/03/20, northbound and southbound Garden State Parkway traffic pattern at Montgomery Street, Milepost 149.7, will be restored to its normal alignment. Work will be supported by State Police.

January 17, 2020

  • During the week of 02/03/20, northbound and southbound Garden State Parkway traffic pattern at Montgomery Street, Milepost 149.7, will be restored to its normal alignment. Work will be supported by State Police.


1

45
46
47
48
49

92

Project Updates

Traffic Alerts

Translate »