Weekly Project Update: April 10, 2020

 In Project Updates

The following work is scheduled over the next three weeks:

GSP ROADWAY AND INTERCHANGE 145 TOLL PLAZA

  • The Garden State Parkway implemented “One-Way Tolling” at Interchange 145. The northbound GSP exit toll at Interchange 145 has been eliminated and the entrance toll has increased.
  • Work zones have been created on the right shoulder of northbound and southbound GSP immediately south of Interchange 145 (milepost 146.5) for Central Avenue Bridge reconstruction.
  • A temporary exit ramp has been opened from southbound Garden State Parkway to Oraton Parkway at New Street in East Orange. The temporary exit ramp provides access to Central Avenue (CR 508) and to Newark via a detour east during bridge construction at Central Avenue. Access to Route 280 remains unchanged. Please refer to the graphic below or CLICK HERE to see full-sized, animated graphics of the detours on the project website.
  • New long-term work zones have been established on the right shoulder of northbound and southbound Garden State Parkway at Springfield Avenue, Milepost 144.7, for bridge related work.

REPLACEMENT OF CENTRAL AVENUE OVERPASS

  • During the week of 04/13/20 through 04/20/20, daytime lane closures on Central Avenue will be utilized in support of PSE&G Electric utility work between Munn Avenue and Hawthorne Place. Work will be supported by East Orange Police.
  • During the week of 04/13/20, traffic will be shifted to the south side of Central Avenue Bridge over the GSP. Two Central Avenue travel lanes will be maintained westbound and one travel lane will be maintained eastbound over the bridge. Eastbound and westbound left turns at Oraton Parkway and Whittlesey Avenue are temporarily prohibited during construction. Please refer to the graphic below for details. Work will be supported by East Orange Police.

ORATON PARKWAY IMPROVEMENTS

  • During the week of 04/20/20, sidewalk and curb reconstruction work will be performed on Whittlesey Avenue. Work will be supported by East Orange Police.
  • A new long-term work zone has been created on South Oraton Parkway northbound, left side, between Central Avenue and Winthrop Terrace. Street parking will be maintained.  Please refer to the graphic below for details.

STRUCTURE NO. 144.7: GSP UNDER CLINTON AND SPRINGFIELD AVENUES

  • New long-term work zones have been established on the right shoulder of northbound and southbound Garden State Parkway at Springfield Avenue, Milepost 144.7, for bridge related work.

STRUCTURE NO. 146.0: GSP OVER 14TH AVENUE

  • No work planned.

STRUCTURE NO. 146.1: GSP OVER SOUTH ORANGE AVENUE

  • No work planned.

STRUCTURE NO. 149.7: GSP UNDER MONTGOMERY STREET

  • No work planned.

STRUCTURE NO. 151.6: GSP UNDER EAST PASSAIC AVENUE (CR 562)

  • A work zone has been created on the south side of East Passaic Avenue between Harrison Street and Milton Avenue for bridge demolition and construction work. Work will be supported by Nutley Police as necessary.
  • The pedestrian walkway over the East Passaic Avenue Bridge has been relocated to the south side of the structure.