Location Highlights

IMPROVEMENTS:

  • Replace the Central Avenue Bridge to accommodate additional auxiliary lanes on the GSP
  • Utility upgrades

CONSTRUCTION:

  • Bridge construction work to be performed in three (3) stages following utility relocations
  • Temporary traffic shifts will be utilized to facilitate the work
  • Short duration temporary detours will be needed during utility relocation work
  • Significant utility relocation work including drainage, water mains, gas mains and electrical facilities will be performed
  • Utility relocation work to begin on or about November 2018

Location Updates

June 21, 2019

  • A work zone has been created on the south side of Central Avenue Bridge over the GSP. Two Central Avenue travel lanes will be maintained westbound and one travel lane will be maintained eastbound over the bridge. Eastbound and westbound left turns at Oraton Parkway and Whittlesey Avenue are temporarily prohibited during construction. Please refer to the graphic below and CLICK HERE to see full-sized, animated graphics of the detours on the project website.
  • During the weeks of 06/24/19 through 08/26/19, PSE&G will be performing significant utility related work on Central Avenue in support of the Project. This PSE&G work will have impacts on traffic between Freeman Avenue and Grove Street.
  • During the weeks of 06/24/19 through 07/08/19, deep foundation work will be performed at the Central Avenue Bridge.

June 14, 2019

  • A work zone has been created on the south side of Central Avenue Bridge over the GSP. Two Central Avenue travel lanes will be maintained westbound and one travel lane will be maintained eastbound over the bridge. Eastbound and westbound left turns at Oraton Parkway and Whittlesey Avenue are temporarily prohibited during construction. Please refer to the graphic below and CLICK HERE to see full-sized, animated graphics of the detours on the project website.
  • During the weeks of 06/03/19 through 08/26/19, PSE&G will be performing significant utility related work on Central Avenue in support of the Project. This PSE&G work will have impacts on traffic between Freeman Avenue and Grove Street.
  • During the week of 06/24/19, deep foundation work will be performed at the Central Avenue Bridge.