Location Highlights

IMPROVEMENTS:

  • Replace the Central Avenue Bridge to accommodate additional auxiliary lanes on the GSP
  • Utility upgrades

CONSTRUCTION:

  • Bridge construction work to be performed in three (3) stages following utility relocations
  • Temporary traffic shifts will be utilized to facilitate the work
  • Short duration temporary detours will be needed during utility relocation work
  • Significant utility relocation work including drainage, water mains, gas mains and electrical facilities will be performed
  • Utility relocation work to begin on or about November 2018

Location Updates

April 5, 2019

  • A work zone has been created on the south side of Central Avenue Bridge over the GSP. Two Central Avenue travel lanes will be maintained westbound and one travel lane will be maintained eastbound over the bridge. Eastbound and westbound left turns at Oraton Parkway and Whittlesey Avenue are temporarily prohibited during construction. Please refer to the graphic below and CLICK HERE to see full-sized, animated graphics of the detours on the project website.
  • During the week of 04/08/19 through 04/15/19, bridge deck demolition will continue on Central Avenue.
  • During the weeks of 04/08/19 and 04/15/19, deep foundation work (pile installation) will begin at Central Avenue.

March 29, 2019

  • A work zone has been created on the south side of Central Avenue Bridge over the GSP. Two Central Avenue travel lanes will be maintained westbound and one travel lane will be maintained eastbound over the bridge. Eastbound and westbound left turns at Oraton Parkway and Whittlesey Avenue are temporarily prohibited during construction. Please refer to the graphic below and CLICK HERE to see full-sized, animated graphics of the detours on the project website.
  • During the weeks of 04/01/19 through 04/15/19, bridge deck demolition will continue on Central Avenue.
  • During the weeks of 04/01/19 and 04/08/19, deep foundation work (pile installation) will begin at Central Avenue.